B1 resort, Ramadani says KEK responsibility

B1 resort, Ramadani says KEK responsibility

B1 resort, Ramadani says KEK responsibility

Alliance MP Burim Ramadani has said that one of the fundamental reasons for the delay of B1 block remont in the Kosovo B thermal power plant is the failure to meet contractual obligations on the part of KEK.

Ramadani has declared that KEK was under obligation to remove scrap and waste, as well as to clean up the share affected by asbestos, but that, according to him, did not.

3M Express sponsor

One of the fundamental reasons why B1’s remont has been delayed turns out that KEK’s share in the contract has had scrip, waste and asbestos removed. And they didn’t. So the responsibility is directly to these, he has declared Ramadan in Dabbat Plus.

His statement comes after accession by Economy Minister Artane Rizvanolli, that B1 will not be restored to office within the set term.

Rizvanolli had said the responsibility for delays belongs to the project contractor, while stressing that the European Union is its contracting and funding authority.

According to the minister, the deadline for completion of the works was November 25th. It had asked the European Union, contractor and the supervisory company to take measures to complete the works as quickly as possible.

Source Layer: Dukeagini

Read more

LVV and LDK become together in Entrance, this is the agreement on sharing positions

LVV and LDK become together in Entrance, this is the agreement on sharing positions

Putin agrees that Europe be included in talks on Ukraine, Witkoff: They’ll attend the next meeting

Putin agrees that Europe be included in talks on Ukraine, Witkoff: They’ll attend the next meeting

Haxhimus: Politicians are misusing citizens’ patience for power cuts

Haxhimus: Politicians are misusing citizens’ patience for power cuts