The Suhareka municipality has cancelled the tender for installing and sanctioning public lighting in several villages in this municipality. The decision comes after newspaper Insander reported on allegations concerning the validity of ISO certificates and the authenticity of documents submitted by the company recommended for the contract.
The certificate company RIGCERT had confirmed to the Insander Journal that the company’s Certificate The LCE SHP.K. was suspended on October 1, 2026, and was reactivated on October 23rd after the annual audit of surveillance was completed. However, the company was recommended for the contract on October 16, 2026, at the time when its certificates were still suspended.

How recommended U.S.P.K. For the contract?
The Suhareka municipality had opened tenders of the projected 490 thousand euros for installation and public lighting in the villages of Savrov, Doberdelan, Bukosh, Sopij, Vrajq, Budakov, Museum, Leshan, Trnje and Komunu.
For this procurement activity, on October 16, 2026, the Communists recommended contracting the company U.S.P.K.
However, to this procurement procedure, there were requirements for reevaluation that the Suhareka municipality had refused.
One of the demands was submitted by an economic operator, who had rejected several tender file criteria, considering them discriminatory, unproportional and restrictive for competition.
Among his claims were the required space for storage and parking equipment, professional experience of the electrolytic engineer, the qualifications of two electrotechnic technicians, documentation for ten workers, ISO certificates of the LCE SH.K. Company, and differences in the prices for the entity submitted in the bid.
The municipality had rejected these claims, arguing that the company’s documentation recommended for the contract met the tender file requirements.
As for certificates I SO, the municipality had said that verification through QR codes in the IGCERT registry had shown that they had the status HINAValid.
Doubts of altered documents IGCERT confirms certificate suspension
In addition to a reexamination request, another economic operator had sent the issue to the Procureing Organisation ( O The Saturday, rejecting the Communist’s decision to recommend the USP.K. for the contract.
In the complaint filed on November 4th 2026, the operator claimed the recommended company had failed to meet some of the tender file criteria and that the municipality had not properly examined the submitted evidence.
One of the main issues filed in the complaint was related to the validity of the ISO certificates of the LCE SH.P.K.
According to the complainers, from verifications into the body electronics system IGCERT certificate, on October 21, 2026, certificates were found with status ♫Spended. The complainer also claimed that on October 22nd he had received confirmation from RIGCERT that certificates were suspended since August 2026.
However, in an answer to the Inseyder Journal, RIGCERT itself had given another chronology on the issue.
According to this certificate body, the certificate of the LCE USPK company. It was first issued on August 26, 2024, while its validity depended on the implementation of annual monitoring audits.
RIGCERT had confirmed that the company had not long completed the planned annual audit, for which its certificates were suspended on October 1, 2026.
A later date, October 22nd, surveillance activities are planned and completed. As a result, the validity of the certificate was restored on October 23rd, said IGCERT’s response to the Insider.
Thus, by the time the company was recommended for the contract, on October 16th, its certificates were still suspended.
Meanwhile, another claim filed in complaints was even more serious. Pollster claims recommended company had submitted a modified Turkish manufacturer’s certificate I RPA AYDINLATMA GIDA.
According to complaint, the document handed over to the tender has added name ARTAY LIGHTTING, who according to the complainers was not a producer but an office through which authorization was provided.
The complainer said that, to verify the authenticity of the document, he had directly contacted the Turkish production company. According to him, it had confirmed that the certificate presented in the tender had been changed and did not comply with the original document.
As evidence, the complainer had delivered the manufacturer’s original certificate, the document presented by the recommended company, communication with the manufacturer, and comparisons between the two documents.
The Suhareka municipality said that it had not dealt with these claims and evidence literally during the review of the request for review.
The complainer claimed that the contracting authority had acted unilaterally, not seeking clarification and giving no recognition for the evidence presented concerning the certificate’s authenticity.
These evidence requires official and impartial verification by the Accounting Authority before continuing with contract connections. While in the AK’s response to the review request, we have not accepted any clarification or assessment of these evidence that we have presented, so we are concerned that the tender assessment commission has acted unilaterally by favouring an OE that is not responsible, the complaint said.
For this reason, the company had asked O The time has come for him to examine the evidence, cancel the Communist decision, and turn the subject into re-evaluation.
With the new decision, the municipality has cancelled the procurement procedure for installing and Sancing public lighting in several of its villages. So the tender for which U.S.P.K. It was recommended for the contract that it will not proceed according to the Communists’ preliminary decision.